|
This is the general scene of the accident. The two locos have plowed through the earth for more than one hundred meters until they were stopped dead in their tracks by a tree, or, maybe I should say stopped dead in no tracks. The two locos and the wagons following them are seen lying in a zig-zag pattern. The white powder seen is the urea, which was being carried in the train.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 819
|
You can see the bogies of the freight wagons as they lie in the trench dug up by the twin WDG-2 locos.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 607
|
This is the second of the twin WDG-2 locos bearing No. 14699 lying
helplessly inside the trench just next to the tree, which was up-rooted by the lead loco. The zig-zag shape of the whole freight train, as it came to halt, can be clearly seen.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 708
|
|
This shows the lead loco bearing No. 14788 of Gooty shed badly damaged after hitting the tree. The tree's stump is lying below this loco. If it were not for this tree, the whole freight train would have proceeded for another 200 or so meters where there was a small nallah. In the opinion of the railway officers, the damage would have been much worse then.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 750
|
The poor dead tree lying next to the lead loco and the second loco.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 637
|
The recovery effort. The crane has been placed on the main line as it lifts one of the crippled wagons from the trench and places it on the other side of the main line. There was a row of trees on the other side of the main line and the crane operator very deftly placed the wagon shells between the trees without causing any damage to such trees.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 597
|
|
This shows the green coloured freight wagon placed between the row of trees and the crane being readied for further recovery efforts. The crane has a capacity of 140 tonnes if the load is within the tracks. When it takes a swing outside, the lifting capacity reduces drastically. Hence, the crane is shifted to the next spot 10 or 15 meters away, re-positioned and re-anchored before lifting the next wagon shell.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 560
|
The recovery of the next wagon shell. The green coloured wagon shell recovered earlier can be seen on the right hand side of the crane partially hidden by the red coloured wagon forming part of the accident relief rake.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 522
|
The scene after all the wagons have been recovered and only the two WDG-2 locos were left for retrieval. The canal-like trench dug by the locos can be clearly seen in this picture. The axles of the freight wagons entangled in the earth are also seen.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 611
|
|
The scene after recovery of all the wagons but before the recovery of the two locos. Gangmen have filled up the trench dug up by the twin WDG-2 locos and a temporary track has been laid right up to the trailing loco to enable the crane to reach the locos. This trailing loco carrying No. 14699, also belonging to Gooty shed was retrieved first. You can also see the senior railway officers standing in the hot sun and planning the next move.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 605
|
The temporary railway track laid up to the trailing loco is clearly visible here. The crane has been brought up on this track with the help of a WDM-2 for retrieving the WDG-2 loco and putting it back on rails. The loco is being readied for lifting on one end by putting hooks on to two eyelets, which carried a warning 'To be used for lifting the loco only in the case of any accident'. The handrails for climbing on to the loco have been cut and removed with the help of gas cutters.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 690
|
This shows the general scene when the loco has been lifted at one end to make the monster hang in mid-air at about thirty to forty degrees with respect to the ground. In the foreground, you can see the main line, which was not affected by this derailment. You can also see some curious onlookers.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 678
|
|
The view of the bottom side of the loco after it has been lifted up. We can clearly see the diesel fuel tank, which got damaged and almost 4000 liters of diesel ran out. The workers are trying to fill up the trench below the loco. This manual effort proved to be inadequate and time-consuming.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 755
|
The earth-mover equipment was brought in, which did a neat and fast job of filling up the trench below the loco. In this picture, you can see this earth-moving equipment in action while the loco has been kept suspended at about forty-five degrees. The railway officers are seen in the foreground and a lot of on-lookers are seen on the other side of the loco.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 574
|
No sooner had the earth-moving equipment filled up the trench and leveled the earth below the loco than the track construction group moved in quickly -- men carrying wooden sleepers, some dragging the new rail, yet others nailing the rail holders on to the sleepers, a couple of them tightening the fish-plates and one lone man verifying the gauge -- to quickly extend the temporary track right below the dangling loco. This track was extended such that the three pairs of wheels of the bogie towards the crane end and at least one pair of wheels of the bogie on the other side would rest on the newly laid rails.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 642
|
|
The gangmen dragging the rail to be laid under the loco.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 543
|
This shows the extension of the temporary track right under the loco as it hangs in mid-air. The earth-moving equipment is seen waiting on one side to be brought into action when the retrieval of the second loco (the lead loco) will have to be done. I stood under this loco for a few minutes and I can tell you that it takes a lot of courage to do so. The two thick wires of the crane actually looked like thin threads when viewed from under the loco. It is not for the weak-hearted chaps to work under these conditions.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 566
|
This photograph shows the temporary track constructed under the hanging (or dangling loco) now almost complete. The PWI and other people are busy fixing the track properly to the wooden sleepers. There was one man carrying the gauge for ensuring that the two rails are exactly five feet six inches apart. All this work was being done by these railway men without any thought to the dangerous monster hanging above. A Damocles sword can only cut your neck. A WDG-2 can crush you to pulp.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 616
|
|
Once the temporary track was completed to reach the four axles of this loco, the loco was lowered slowly on to the freshly laid track. The skill and expertise of the crane operator is paramount here, who has to give the right amount of swing to align the loco to the track and then lower it gently on to the track.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 623
|
This shows the loco being lowered further with anxious railway men closely monitoring the operations and giving feed back to the crane operator. The crane operator sits inside the driving cab of the crane. There was a crane supervisor holding a walkie-talkie radio in his hand for getting feedback from the PWI and others surrounding the loco being lowered on to the tracks. The crane supervisor gave further directions to the crane operator.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 563
|
The loco is now properly aligned and almost fully lowered on to the tracks. You can see the last axle and its two wheels just before it came to rest on to the tracks. You can also see the rails fastened together with the help of a fish-plate with only one bolt on each side. At some joints, where holes were not available in the rail for the bolts, only one bolt was used to hold the fish-plate and the rails together. In this instance, the two rails would have a gap of about an inch to allow the passage of the bolt. This temporary arrangement was adequate to retrieve the loco at slow speed.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 573
|
|
After the four axles of the loco were lowered on to the newly laid set of tracks, the crane was pushed further by the WDM-2 until the crane was able to couple to the WDG-2. Now, the brute force of the WDM-2 was used to forcibly drag the crippled WDG-2 on to the tracks and beyond to the loop line. The WDM-2 was powered up to Notch-5 in gradual steps without any movement at all. The re-railment of the WDG-2 needed notch 6 power in the WDM-2. With this action, the recovery of one WDG-2 was complete.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 554
|
This photograph shows the commencement of the recovery operations for the lead loco No. 14788. It is sunset time and the rest of the recovery operations were carried out under floodlights.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 543
|
This photograph shows the lead loco hoisted up at an angle of forty-five degrees. The earthmover was already in action to fill up the trench or ditch and level the ground under this loco. It was dusk at this moment and, in a few more minutes, the floodlights were switched on with the help of portable generators. The rest of the recovery operations were conducted in darkness with the second loco being retrieved at about 8.45pm.
Date: 2004-11-08
Owner: Gallery Administrator
Views: 560
|